Completion of SMG work

District: 
Jumla

Specific maintenance work through specific maintenance group (SMG) has been completed in jumla. Under direct funding of RAP3, 76 SMGs members (male -42 and female-34) were involved in three different groups in three different DRCN roads. Approximately 80% of physical progress and financial progress (including cost of construction tools, materials, safety gears, civil work and management) has been estimated to be achieved. DTA has prepared final bill of SMG members and sent to TMO for review. Analyzing the feedback of SMG members during questionnaire, it looks like they are happy and willing to work as SMG in RAP3 for further specific maintenance activities. DTO/DCC is well satisfied with SMG work and RAP3 working modality and encouraging DTA to continue such maintenance activities in the DRCN roads of the district.